Welcome to the eighth issue of the 5 Broadgate Update. This publication aims to keep you Involved in and informed of the development of this construction project and the works planned over the next few months.
What’s happened?
• The capping beam works on the Broadgate Estates/Network Rail ramp have been completed and hoarding re-aligned
• The bulk excavation has continued and is now 55% complete
• Concrete works to the raft have commenced and the first two sections have been completed
• Tower Crane 3 was erected successfully and is now fully operational
Future developments?
• Condenser alteration works over the Network Rail ramp will start mid in October, running through the day and night and over a number of weekends, whilst maintaining access to the ramp
• Bulk excavation will continue during the month with a further 2000 lorry loads to be removed
• Concrete works to the raft slab will continue, with a number of large concrete pours planned to be carried out over-night, first one planned for 05/06 October
• Tower Crane 4 will be erected on the 13th and 14th October 2012
If you have any suggestions or queries please do not hesitate to contact our team.
Mandeep Tiwana
Senior Construction Manager
Mandeep.Tiwana@macegroup.com
07887747371 – 24 hour contact
Robert Dudley
Deputy Project Director
Robert.Dudley@macegroup.com
07801621702
Mace Project Office
The Pavilion
3 Broadgate
London
EC2M 2QS
Hours Mon – Fri 08:00m to 18:00
Tel: 0208 256 9500
There are no comments.